Project Name/ Location Postcodes Description Impact to water supply Start Date Finish Date
P023075 - Dunmow Reinforcement CM6 2JL Installing new pipelines No Jul-24 Feb-25
P021672 - Harefield to Oxhey Wood HA5 3 Renewing strategic pipelines No Jan-24 Sep-24
P023043 - Preston Road HA9 8 Renewing existing pipelines No Jan-24 May-24
PO21766 - Ashley Green HP5 3 Renewing strategic pipelines No Oct-23 Aug-24
P022035 - Hamilton Road, Southall UB1 3BQ Installing new pipelines Yes Aug-24 Sept-24
P022995 - Penn Road HP15 Installing new pipelines No Jul-24 Sep-24

This page was last updated on: 26 June 2024